Potable Water Source Feasibility Assessment - North Peace Park
The Peace River Regional District (PRRD) is exploring the feasibility of the groundwater at the North Peace Park as a source of long-term drinking (potable) water for Electoral Area B.
Building on previous studies, the feasibility assessment will look at:
- Amount and quality of groundwater available
- Possible locations for a new well
- Whether the water can be treated using the existing Rose Prairie Water Station
- Additional infrastructure and/or future work that may be needed
Plan Status and Next Steps
McElhanney, a consulting firm, is currently assessing the site to better understand the available groundwater and requirements for developing a new water source. This work includes reviewing existing information, infrastructure and completing field investigations.
Work is expected to begin in late 2026 and continue into 2027. The results will help the PRRD decide whether North Peace Park is a suitable location for a future community water source.
Timeline
- July to September 2026: Project is initiated and sent out for procurement
- October to December 2026: Procurement contract awarded to consulting firm, McElhanney
- October to December 2026: Hydrogeological review and regulatory assessment work
- January to March 2027: Feasibility assessment report to be presented to the Regional Board
- January to June 2027: If the groundwater is deemed feasible, well drilling and testing to be conducted
- March to June 2027: If the groundwater is deemed feasible, water quality and compatibility assessment to be conducted
- March to June 2027: Final technical reporting and project close-out work
Frequently Asked Questions
View the frequently asked questions about the North Peace Potable Water Source Feasibility Assessment. You can the email the Environmental Services Department if you have any other questions or need more information.
Will this assessment guarantee a new water station?
Why can't the existing well be used as a community water source?
Previous assessments identified issues with the existing well that would require significant upgrades to meet current groundwater protection requirements. As these upgrades are not considered feasible, the project will explore options for a new well.
What happens if the water source is not suitable?
The assessment will determine whether North Peace Park is a suitable community water source. If it is not, the findings will help the PRRD consider other options for providing a reliable, long-term drinking (potable) water supply.